Project: Expand Mini Mall & Food Court, JBLM

Client:Army AirForce Exchange Services
Location:Joint Base Lewis-McChord
Final Completion Date: October 2011

The North Ft. Lewis Mini Mall consisted of an 7,200 square foot addition and remodel, which was performed in phases to allow uninterrupted retail operations. Pease expanded the current facility by adding new retail space and expanding the food court seating area. Existing food concepts were also upgraded with new fixtures, finishes and equipment. Exterior improvements were modified to the mini mall, which included asphalt concrete, paving, curbs and sidewalks. Pease completed the Burger King modifications in just three weeks, instead of the two month schedule the owner allowed for. The $2.4 Million project was completed in July 2011.
     
 
 
 